VGH Medical Device Reprocessing Department Construction Update
Construction to expand and renovate the Medical Device Reprocessing Department (MDRD) at Victoria General Hospital (VGH) is scheduled to begin in November 2026, with work expected to continue through March 2028.
The project will take place in four phases, beginning with the relocation of a storage room to the Hospital at Home area. Subsequent phases will include the demolition of meeting rooms adjacent to the cafeteria to create a new Environmental Support Services (ESS) area, followed by the demolition of the existing ESS area to accommodate the MDRD expansion.
The final phase will involve renovations to the MDRD, with a temporary STERIS trailer installed outside to support operations during construction.
→ Construction Phases
The work will be completed in four phases to support the expansion and renovation of the MDRD while maintaining operations during construction.
- Relocation of a storage room to the Hospital at Home area.
- Demolition of meeting rooms adjacent to the cafeteria to create a new Environmental Support Services (ESS) area.
- Demolition of the existing ESS area to accommodate the MDRD expansion.
- Renovations to the MDRD, supported by a temporary STERIS trailer installed outside.
Kinetic Construction is the construction manager for the project.
What staff need to know
Phase 1 is expected to run from November 2026 through February 2027 and will affect the cafeteria area and doors connecting to staff parking.
Staff are encouraged to use alternate entrances and exits during this period to help minimize congestion and avoid construction-related disruptions.
Thank you for your patience and cooperation as this important work gets underway. Further updates will be shared as the project progresses.